District Development Name Developer No. of Residential Source of
Units GFA (sqf) land
Eastern Victoria Harbour Phase 2 Sun Hung Kai Properties 351 258,000 Redevelopment
Eastern Novum Point Henderson Land’s family 281 85,000 Redevelopment
Central & Western 1-19 Chung Ching Street Henderson 264 79,000 Redevelopment
Central & Western 150-158 Queen’s Road West Circle Property 132 40,000 Redevelopment
Central & Western 21 Borrett Road Phase 2 Cheung Kong 66 149,000 Rezoning
Central & Western 75 Peak Road Season Glitter Ltd. 13 29,000 Redevelopment
Central & Western 47 Barker Road CSI Properties 1 2,000 Redevelopment
Southern 72 Repulse Bay Road First Group 1 18,000 Redevelopment
Central & Western 36 Severn Road Nulima Company Ltd. 1 9,000 Redevelopment
Hong Kong Sub-total 1,110 669,000
2020 Total 18,383 11,723,000
Notes: 1. The date of completion is defined as the date of obtaining the Occupation Permit. The expected date is sourced from the sales bronchure of the
project, disclosure from presale consent application and public disclosure from developers. In the case that these are not available, the completion
date will be based on our estimates with regard to information from the Buildings Department, the Town Planning Board and site inspection.
2. In the case that the number of units are not publicly available from the government or developers’ disclosure, OHKF estimated the number based on
the average unit size of adjacent projects from the same developers in recent years.
Sources: Buildings Department, Lands Department, Town Planning Board, developers’ financial reports, various newspapers and Our Hong Kong Foundation