involved in these development projects, they all require an exceedingly long
              lead-time.

              3.2 Exceedingly Long Lead-time of

              Development


                     As Table 4 shows, currently the development lead-time, defined
              as the time needed from the project being tabled for the District Council’s
              consideration to its completion, for public housing projects exhibits a wide
              range from 55 months (4.6 years) to 139 months (11.6 years).

              Table 4. Development lead-time of selected public housing projects



































































               Note      :     (*)  Refers to the time between consultation with the District Council and completion of the project.
               Sources:    Transport and Housing Bureau, Legislative Council, District Council, and press reports.