After examining in detail the 69 sites to be rezoned, we conclude that the Government should prioritise and
                 expedite the process for at least 25 of them. Minor site formation and tree removal may be required for certain
                 sites but majority of these sites remain technically feasible to be rezoned. (Please refer to Appendix III for
                 the list of sites and details)


               Moreover, we found that another 25 sites may be challenging in their rezoning process and/ or other processes
               afterwards. Among these 25 sites, 15 of them are “brownfield” sites with existing operators. Developing these sites
               will inevitably involve the complicated processes of land resumption, relocation and compensation.
               The rezoning difficulty of the remaining 19 sites may not be ascertained at the moment as it will be conditional upon
               further studies on key factors including the availability of the site, neighbourhood capacity, impact on the environment
               and other technical constraints etc.