3-year waiting time target is just chasing rainbows




























                             Unfortunately, even if the Government reaches their public housing completion target as laid out in the LTHS (i.e.
                             31,500 units per year), it will still take an estimated 10 years’ time for the PRH General Applicants’ average waiting
                             time to be within 3 years.
                             As aforementioned, we estimate that only about 230,000 public housing units are likely to be completed over the
                             period,  equivalent  to  23,000  units  on  average  per  year.  In  that  case,  we  estimate  the  3-year  target  will  only  be
                             achieved after at least 30 years.

                                If we are to achieve the 3-year waiting time for a PRH flat within the next five years, like we did in
                                the past, we estimate that at least 43,800 public housing units will need to be built on an annual
                                basis, which is 1.4 times higher than the forecasted completions of 18,300 units.