In the past five years, delays in public housing
                                       completions have intensified





























                        As  previously  said,  public  housing  development  projects  have  been  plagued  by
                        delays.


                     By comparing the time lapse between the planned completion year and actual completion of public
                     housing projects, we find that for the past five years, the number of units that were delayed have
                     increased. In particular, of the units completed in 2018/19, 23,100 units (84% of the completions in
                     2018/19) had experienced different degrees of delays.